Turnkey Warehouse Setup
Location: Homestead, FL
Date: July 24, 2023
Project Type: Full Multi‑System Installation and Operational Integration
Client Background
A warehouse operation located in Homestead, FL required a fully turnkey setup to support inbound product receiving, SKU organization, multi‑level order picking, and controlled access. The customer sought a unified installation that would eliminate reliance on temporary staging methods, reduce handling inefficiencies, and support scalable inventory growth. The warehouse needed immediate operational activation without phased or delayed deployment.
Project Overview
The objective of this installation was to deliver a complete ready‑to‑operate warehouse environment. The scope included integrating multiple rack and access systems tailored to support multi‑level storage, optimized SKU accessibility, and controlled movement within the facility. Dock‑to‑picking pathways and elevated access systems were required to enable efficient inbound and outbound handling.
Project Challenges
-
Multiple storage formats needed to be combined to serve varied inventory and SKU handling requirements.
-
Material staging and placement had to be performed in a way that preserved forklift travel lanes and operational mobility.
-
Folding security systems needed to be integrated with structural rack elements to support controlled facility access.
-
Immediate operational readiness was required, with no allowance for sequential or delayed stages.
Solution and System Implementation
Bogardus delivered and installed a full turnkey solution including:
-
Rivet shelving installations for organized SKU-level access
-
Heavy-duty pallet rack systems for vertical storage and pallet staging
-
Folding security gates to control access and enhance facility safety
-
Full dock ramp integration to support receiving operations and inbound freight movement
-
Rolling ladder systems designed to facilitate safe multi‑level access for picking and inspection
Material delivery and installation sequencing were coordinated to allow active facility movement throughout deployment. Final system alignment, anchoring, access pathway clearance, and safety integration work were completed to ensure immediate warehouse functionality.
Results and Outcomes
-
The customer received a fully operational warehouse layout configured for efficient multi‑level picking and storage from the first day of activation.
-
Workflow efficiency improved through designated shelving, pallet rack allocation, and controlled traffic pathways.
-
Facility safety improved through the integration of rolling ladders and secure access control systems.
-
SKU accessibility and staging organization were significantly enhanced due to the combination of shelving and pallet racking.
Long‑Term Impact
The turnkey configuration provided a structured foundation for scalable operations, enabling the facility to handle increased inventory volume and SKU diversity without reconfiguration. The integrated dock ramp, access ladders, and secure entry systems delivered lasting operational stability, enhanced safety performance, and improved inbound processing efficiency.